Case study · GracePoint Wesleyan Church · 2016–2018
I owned the AV and low-voltage side of a 19,609 sq ft, two-story church addition, from design through installation, and delivered about $250K in AV systems on budget.
| Organization | GracePoint Wesleyan Church, Brookings, SD |
|---|---|
| Years | 2016–2018: about 8 months of design, groundbreaking in October 2016, ribbon cutting in October 2018 |
| My role | Owner's representative for AV, electrical and low-voltage; system designer; lead installer |
| AV budget | About $250K, landed on budget (part of a roughly $3M building project) |
| Spaces | 350-seat great room, upstairs kids worship space and check-in, 30-seat chapel, 4 preschool classrooms, and AV and network for the whole addition |
| Worked with | designArc (architect), Mills Construction (construction manager at risk), electricians, a local AV company, Worlds of WOW (themed kids environment), church leadership |
The church needed one new room that could work three different ways, plus space for kids and preschool.
It also had to tie into the existing building's sound and network, share audio with the main worship center, and stay inside a fixed AV budget.
I owned the electrical and AV side of the project for its full two-year build, from the first design meetings through completion, and installed the systems myself.
The great room was designed to switch between live, video and event use with a few presets, and the rest of the addition got simpler, reliable systems.
| Space | Audio | Video | Lighting and control |
|---|---|---|---|
| Great room (350 seats) | Soundcraft Si Impact console, BSS Blu networked DSP, Crown amps, JBL 3-way PA with flown subs, full-band in-ear monitor system, stage boxes, 4 wireless mics, Dante link to the main worship center | 3 motorized screens driven by an SDI switcher and ProPresenter, plus a stage display. Side screens show slides or tight camera shots; the center screen drops to the floor for a life-size shot of the main stage, or stops higher for movies and simulcasts | Jands Vista console, 4 ellipsoidals, 12 RGB zoom wash fixtures, Lowell power sequencing for one-touch startup and shutdown |
| Kids worship space (upstairs) | Soundcraft Ui24 console, flown EV speakers with flown subs, 2 wireless mics | Large TVs driven by ProPresenter on a Mac mini | 8 RGB wash fixtures on the stage |
| Preschool classrooms (4) | None | Simple TV setups | None |
| Network | Cabling coordinated with electricians | New wing tied into the existing UniFi system | Configured to match the rest of the building |
The great room was acoustically treated, with wall tiles and a sprayed absorptive ceiling, to tame the room and cut sound to the floor above. To stretch the budget, I bought brighter laser projectors for the main worship center and moved its older projectors into the great room, where they were bright enough and the main room got lower maintenance.
The rest of the addition got AV too: speakers in the 30-seat chapel, and touchscreen computers with label printers built into the kids check-in counter. Up to 64 Dante channels can pass between the great room and the main worship center. One Christmas, a second sound tech in the great room mixed every input from the main stage into a separate mix made for that room, while the band and message came in by video.
The biggest problem was sound from the kids space upstairs carrying into the great room below, a risk I had raised during design.
The AV came in at about $250K, on budget, and the great room is still in weekly use years later.